Ikoyi building
Advertisement

Lagos State Government, on Thursday, announced its readiness to demolish the three uncompleted high-rise buildings on the site of a 21-storey building that collapsed on Gerrard Road, Ikoyi, last November.

The state government said the demolition became necessary after the buildings failed integrity tests.

It noted that a structural engineering firm, Edge of Design, would demolish the twin 14-storey and eight-storey structures on the site in a manner that will not pose any health or environmental hazards to residents in the neighbourhood.

The deconstruction, which is expected to be completed within 90 days, would be supervised by relevant agencies of the government and private stakeholders in the built industry.

The development, it was learnt, was part of the recommendations by a six-man panel that investigated the collapse of the 21-storey structure owned by Messrs Fourscore Heights.

The land on which the failed structures sit has been forfeited to the state government by law. The panel also recommended criminal prosecution of the developer for contravening the State’s building codes.

No fewer than 45 persons, who were mainly construction workers and vendors, died in the incident.

Also, the developer, Mr Femi Osibona, died in the collapsed building.

Representative of the contractor, Edge of Design, Mr Olujimi Lewu, explained the step-by-step process to be employed in bringing down the structures, saying the work would be done without any injury or fatality.

The Lagos State Commissioner for Information and Strategy, Mr Gbenga Omotoso, at a press briefing held at the Bagauda Kaltho Press Centre in Government Secretariat in Alausa, on Thursday, said safety would be the main consideration in the deconstruction.

READ ALSO: One dead as another building collapses in Lagos

Omotoso said the press conference was in the spirit of transparency for which the Governor Babajide Sanwo-Olu administration is known for.

He stressed that the deconstruction was agreed upon after extensive consultations with stakeholders, residents and regulators in the built industry.

The commissioner assured residents in the neighbourhood of their safety throughout the exercise, noting that measures had been put in place to ensure that the contractor maintains the agreed safety protocols.

“The deconstruction will be done with one key focus from all stakeholders; this is safety of people in the neighbourhood and everybody that will be working on the site. The recommendations of the panel are being implemented to prevent this kind of incident,” Omotoso said.

On his part, the Commissioner for Special Duties, Mr Tayo Bamgbose-Martins, a civil engineer, assured all that reports on the deconstruction would be regularly shared with the public, describing the contractor as competent.

Also speaking at the event, the Lagos State Commissioner for Physical Planning and Urban Development, Dr. Idris Salako, disclosed the reason the state government took over the property, saying: “Section 74 of the Urban and Regional Planning and Development Laws of Lagos State 2019 (as amended) prescribes that any property that collapses in the State is automatically forfeited to the Government.”

Salako said the state government had not decided on what to do with the site after the deconstruction.

He said: “When the state government is ready to revive the site, we will let the public know what we want to do with it.

“However, I can assure you that the land will not be given to any individual developer or converted to unapproved use by the government. The site will be used for something that will be of benefit the public,” the commissioner said.

The Star

Advertisement

LEAVE A REPLY

Please enter your comment!
Please enter your name here