an inspection tour of the rehabilitation project, which also coincided with the 15th Refineries' Rehabilitation Steering Committee Meeting.
The Nigerian National Petroleum Company (NNPC) Ltd. has completed the mechanical rehabilitation work on Area 5 Plant of the Port Harcourt Refining Company (PHRC).
Rehabilitation work has been ongoing at the Refinery for over two years and the NNPC Ltd. had pledged to complete Phase One of the project (mechanical completion and flare start-up) of Old Port Harcourt Refinery (Area 5) by 31st December 2023.
Group Chief Executive Officer, NNPC Ltd., Mr. Mele Kyari, said as of December 15th, 2023, 84.4% of Area 5 Plant, a key component of the refinery, and 77.4% of the entire rehabilitation project have been completed.
Kyari spoke on Thursday, December 21, during an inspection tour of the rehabilitation project, which also coincided with the 15th Refineries’ Rehabilitation Steering Committee Meeting, the
“In our quest to ensure that this refinery is re-streamed to continue to deliver value to Nigerians, we made a promise that we will reach a mechanical completion of phase one of the rehabilitation project by the end of December and get the other plants running in 2024. Today, we have kept those commitments,” Kyari stated.
The GCEO commended the NNPC Ltd.’s staff and the EPCIC contractors for doing a great job in ensuring that the refinery achieved that significant milestone.
In his remarks, the Chairman of NNPC Ltd Board, Chief Pius Akinyelure described the milestone as “historic”, stressing that the board was proud of the staff and management of the refinery.
“We are just starting. We want to be at the highest level of production so that we will keep the prices of petroleum prices in the country stable in order to give comfort to our people and generate more revenue for our country,” Akinyelure noted.
FG: P/Harcourt refinery resumes production in December
Also speaking, the Minister of State for Petroleum Resources (Oil), Senator Heineken Lokpobiri, said the milestone is another landmark of the renewed hope agenda of President Bola Tinubu.
He thanked Nigerians for their patience and the trust they have in NNPC Ltd.’s ability to deliver on this huge project.
Minister of State for Petroleum (Gas), Rt. Hon. Ekperikpe Ekpo, said re-streaming the refinery will herald a good omen for the nation’s Liquefied Petroleum Gas (LPG) industry, as LPG, also known as cooking gas, is a major bye-product of the Refinery.
Also speaking, the Managing Director of Tecnimont Nig. Ltd., Fabio Del Cioppo, one of the EPC Contractors of the Rehabilitation Project, said his company remains committed to fulfilling the terms of the contract.
Chief Corporate Communications Officer of NNPC Ltd., Olufemi O. Soneye, said the PHRC rehabilitation project, which costs about $1.5 billion, is an EPCIC project that covers Engineering, Procurement, Construction, Installation, and Commissioning phases.
“For Area 5, the Engineering, Procurement, Construction, and Installation have all been completed. The mechanical completion signifies the closure of the Construction and Installation phases.
“More importantly, the milestone was achieved under an excellent Health, Safety and Environment (HSE) record, which stood at over 9.5 million manhours with zero Loss Time Injury (LTI),” Soneye said.
The Senate has fixed March 17 for final consideration and passage of the N58.472 trillion…
The Fusengbuwa Ruling House has defended its initial decision to set the application fee for…
The Taminu Turaki-led National Working Committee of the Peoples Democratic Party (PDP) says it has…
Veteran Nigerian singer Oladapo Oyebanjo, widely known as D’banj, has gifted a new car worth…
The Benue State Government has warned private school owners against imposing what it described as…
Two men have been killed following fresh violence linked to a long-running land dispute between…
This website uses cookies.