The Lagos State Government has announced the temporary closure of Iddo Bridge in the Ijora area of Apapa Local Government Area for five days to facilitate ongoing rehabilitation and reconstruction works on the bridge.
The Commissioner for Transportation, Oluwaseun Osiyemi, said the closure would enable the Federal Ministry of Works to install heavy steel bridge beams as part of the reconstruction project.
According to him, the operation will take place between June 17 and June 21, 2026, with work scheduled from 10:00 p.m. to 5:00 a.m. on some days and from 8:00 a.m. to 4:00 p.m. on June 21.
Osiyemi said the entire section of Iddo Bridge would be temporarily shut to vehicular movement during the periods to ensure the safe installation of the steel beams.
He explained that the closure forms part of traffic management measures put in place to support the launching of steel beams for the rehabilitation project being executed by the Federal Ministry of Works through the Office of the Federal Controller of Works, Lagos.
The commissioner urged motorists to exercise patience and cooperate with traffic management officials during the temporary closure.
By GARBA SHEHU There are good reasons why Leno Adesanya and his company, Sunrise Power…
A 400-level student of Ibrahim Badamasi Babangida University, Lapai (IBBUL) in Niger State, Isma’il Ishaq…
The by-election for the Dawakin Kudu State Constituency in Kano State recorded low voter turnout…
The Anambra State Ministry of Justice is reviewing about 180 criminal cases arising from land…
Bandits who kidnapped six Islamic clerics in Zamfara State have demanded N30 million for their…
Former House of Representatives Minority Leader, Farouq Aliyu, has alleged that he was offered N250…
This website uses cookies.